Free CPIM-MPR – Certified in Production and Inventory Management - Master Planning of Resources Practice Test Question

Free demo downloads

Loading demo links...

Showing 7–9 of 10 questions

Question 7

The question below is based on the following information:

C:\Pasban Work\Cert Paper Exams\APICS\CPIM\481_2352_graphic.PNG

Which of the following distributions would be the central warehouse allocation of 120 units of inventory to district warehouses A, B, and C if the equal run-out method were used?

Select an option, then click Submit answer.

  • ○

    20 units to A, 53 units to B, 47 units to C

  • ○

    20 units to A, 60 units to B, 40 units to C

  • ○

    20 units to A, 80 units to B, 20 units to C

  • ○

    100 units to A, 0 units to B, 20 units to C

Question 8

An outcome of top management's participation in sales and operations planning involves the:

Select an option, then click Submit answer.

  • ○

    delegation of trade-off resolutions to middle management.

  • ○

    investigation of detailed trade-offs by top management.

  • ○

    definition of trade-offs by top management.

  • ○

    resolution of broad trade-offs by top management.

Question 9

The primary task of demand management in an assemble-to-order environment is to define the:

Select an option, then click Submit answer.

  • ○

    customer's order in terms of specific components and options.

  • ○

    raw materials required to complete the customer's order.

  • ○

    availability of inventory to meet the customer's order.

  • ○

    customer's order in terms of product families.