Question 1 (Topic 1)

How would a master production schedule (MPS) be used in an assemble-to-order (ATO) manufacturing environment?

Select an option, then click Submit answer.

  • The MPS is used to plan subassemblies and components; end items are only scheduled when a customer order is received.
  • Subassemblies are scheduled in the MPS when the customer order is received, and production can start.
  • Typically, the MPS is not used in companies using an ATO manufacturing strategy.
  • Often in an ATO environment, the MPS is created once a year and only revised if a product is discontinued.
Question 2 (Topic 1)

A benefit of utilizing a transfer batch would be that it:

Select an option, then click Submit answer.

  • reduces the number of changeovers needed.
  • allows multiple work centers to be working on the same shop order.
  • allows its batch size to match the customer order size.
  • reduces transportation costs between operations.