How would a master production schedule (MPS) be used in an assemble-to-order (ATO) manufacturing environment?
Select an option, then click Submit answer.
- ○ The MPS is used to plan subassemblies and components; end items are only scheduled when a customer order is received.
- ○ Subassemblies are scheduled in the MPS when the customer order is received, and production can start.
- ○ Typically, the MPS is not used in companies using an ATO manufacturing strategy.
- ○ Often in an ATO environment, the MPS is created once a year and only revised if a product is discontinued.