Question 10

The equivalent of a cost reimbursable contract is frequently termed:

Select an option, then click Submit answer.

  • ○

    back-charge contract.

  • ○

    fixed price contracts.

  • ○

    progress payment contract.

  • ○

    cost plus contract.

Question 11

The risk contingency reserve is identified in which process?

Select an option, then click Submit answer.

  • ○

    Estimate activity duration.

  • ○

    Estimate costs.

  • ○

    Determine cost baseline.

  • ○

    Estimate activity resources.

Question 12

The project is delayed and according to the customer contract, Nokia is due to pay a penalty. What is the recommended approach?

Select an option, then click Submit answer.

  • ○

    Accept the customer penalty and apply for compensation from an insurance company.

  • ○

    Renegotiate the contract.

  • ○

    Contract change process.

  • ○

    Claim strategy and understanding of contractual obligations.