Question 19 (Volume D)

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

Select an option, then click Submit answer.

  • Applying calendars

  • Resource leveling

  • Resource planning

  • Resource conflict management

Question 20 (Volume A)

Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?

Select an option, then click Submit answer.

  • External

  • Internal

  • Mandatory

  • Discretionary