The following requirements were identified in an architecture workshop for a virtual infrastructure design project: REQ001: All virtual machines must meet the Recovery Time Objective (RTO) of twenty-four hours or less in a disaster recovery (DR) scenario. Which two test cases will verify these requirements?
Select an option, then click Submit answer.
Reference / correct answer:
Simulate or trigger an outage of the primary datacenter. All virtual machines must be restored within twenty-four hours or less.
Most accepted answer: A. Simulate or trigger an outage of the primary datacenter. All virtual machines must be restored within twenty-four hours or less.
Community votes: A=5, B=1, C=2, D=1
Selected Answer: A just 1 answer is required on exam upvoted 2 times
Selected Answer: AC A. Simulate or trigger an outage of the primary datacenter. All virtual machines must be restored within twenty-four hours or less. This directly tests the RTO, which measures how quickly systems must be restored after a disaster. It confirms that recovery operations complete within the acceptable time window. C. Simulate or trigger an outage of the primary datacenter. All virtual machines must be restored within four hours or less. Although more aggressive than the stated RTO, this test still validates compliance with the requirement. It demonstrates that the infrastructure can recover well within the 24-hour threshold. upvoted 1 times
Selected Answer: AC B&D is RPO So it should be A&C upvoted 1 times
Selected Answer: AD RPO term is missing in the requirement. on the basis of that we can decide the time interval of securing the data . I must believe you will get the RPO value four hours in the exam and that time your right choice should be A & D. upvoted 1 times
Selected Answer: AB I'd say A and B upvoted 1 times