Question 7 (Topic 1)

A customer is deploying VCF at a new datacenter location. They will migrate their workloads from the existing datacenter to the new VCF platform over six months. Both datacenters will run simultaneously for six months during the migration. Which of the following should be a documented risk?

Select an option, then click Submit answer.

  • Six months may not be enough time to complete the migration.
  • There will be connectivity between the two locations.
  • Bandwidth between the two locations is sufficient to accommodate the workload migration.
  • Workloads will be powered off during migration.